Injection Mold Operation Guidelines

Injection Mold Operation Guidelines


 

1. Check the mold mounted water chew and rings
1.1 To check the size of the mold and mounted the water chew. Rings with suitable machine;
1.2 To check whether the AB mode is tighten up the lock plate.
2. Installing the mold machine
According to the direction of the arrow shown on the mold to lift the mold between dynamic and fixed template of injection molding machine, using the flange of the mold to imported into the positioning hole of the injection molding machine fixed template firstly, and then closed the board, so that the mold close to the two boards. Not reverse placed the mold if no special circumstances during normal use.
3. Cleaning and checking mold
After installing the mold, to separate the cavity and core insert and to clean the anti-rust oil and oil stains of the cavity with cleaner, to check the surface of the cavity if normal.
4. Debug mold action
4.1 operating beer machine debugging to the appropriate schedule, set the appropriate parameters of plastic beer mold repeated opening and closing times debugging the top line spaces and mold movements smooth before they can begin production;
4.2 in accordance with this tone machine parameter list and the tryout report conditioners.
5. Guidelines for debugging according to the mold action
Details please refer to the next article mold production and action guidelines.
6. Completed production tasks to prepare for taking down the mold
Before completed production tasks to prepare for taking down the mold, the mold cooling system equipment should be turn off, and the products should be produce 10-20 shots to evaporate the water inside the cavity.
7. Clean mold and spray anti-rust stains
The mold closed prior to clear the dust on the cavity surface of the mold parting surface, spray the right amount of green rust-proof oil to clean the stains and then closed the mold.
8. Disassembling the water pipes
Throw the water pipes and use the air gun to blow clean the residual moisture in the transport water hole, to prevent water oxidation and rust to clog water transport.
9. Take down the mold
Tighten up the lock plate and take down the mold, the mold should be placed in a dry ventilated place to prevent damp and rust to affect the life of mold.